Construction update: Sep 2016

The inoculation phase is almost finished, which means: the digester is filled with a mix of organic waste from public toilets, slaughterhouses and food markets from Ashaiman. This waste produces biogas, and the amount of biogas in the green balloon … Continue reading

Ashaiman construction update: March 2016

This month the construction of the digester is practically finalized. The large 27x27m square cavity was first covered with white felt to protect the black impermeable membrane at the bottom.       In the middle a pole supports orange … Continue reading